Henan Liming Heavy Industry Science & Technology Co.,Ltd
News  >  features >  Installation Manual cone crusher

Installation Manual cone crusher

13. Adjustment device adjustment packages, the installation of spring
(1) sets will be supported adjustment ring cleared. Sawtooth-shaped thread in the dry Tu dilute mixture of oil, fuel tanks will be installed in the Lock supporting put locking cylinder interface department had received hydraulic station on the Department of the interface. (See drawings)
(2) Supporting the rack-mounting kit.
(3) The adjustment will be rotating into supporting Inner Ring.
(4) locking nut twisting in supporting put, at the pin hole into the four pin.
(5) Installation of devices and funnel funnel.
(6) Installation Coverer: Installation Coverer, attention to the adjustment of the four key ring block, in the dust cap the card slot.
(7) drawings provided by the work of a high degree of adjustment H spring.
(8) Installation of tanks to promote livestock potential, as shown in Figure 13 by the installation location to promote good cylinder, the cylinder to promote two interfaces from M and N respectively hydraulic station interface M and N, animals potential for Figure 12 Tube clip shown in the feed of the pillars, animals potential interface through heart-locking hose and Stone received in the cylinder Circuit.


14. Feed the installation of the Department of
(1) improper installation of the crusher will have the following effects.
A crusher to reduce output.
B uneven discharge particle size, bulk and more.
Wear Parts C or uneven wear accelerated wear.
(2) distribution of the feed from the mouth of a high degree of H-crusher on the normal work is important, too high when H ore is not easy to direct the allocation of disk space to the crusher, therefore, must be in accordance with the regulations of the high degree to install it.
(3) radial plate is meant to protect the feed box is not damaged and ores difficult in the feed box to plug in the installation need to maintain the shape and curved steel plate curved mouth feed from the edge of the size, so as to avoid accumulation Ore.


15. Hydraulic station installation and adjustment of pilot
(1) crusher on the hydraulic station on the basis of the appropriate position to facilitate the operation of hydraulic station Unicom mainframe components of the pipeline and the Chin, the actual situation may be appropriate site layout.
(2) Hydraulic Station M, N, P 3 I promote cylinder with the M, N mouth to mouth P locking cylinder and connecting.
(3) Hydraulic Station ministries installed after pressure test, the test pressure of 140 kgf/cm2.
(4) locking test.
A cylinder lock to be suppressed prior to the animal-derived income potential 75-80 kgf/cm2 nitrogen.
B must be relieved after the cylinder to promote locking cylinder pressure.
C in the test locking cylinder and the residual gas pipeline, or in the pipeline ready to help at the bottom of the Beaufort blocking excluded.
(5) Adjustment Test: relieved after the lock cylinder used to promote cylinder adjusted discharge mouth tests.
(6) achieved good hydraulic station components, flexible manipulation. Figure 16 points for the hydraulic diagram.


16. Load test
(1) after idling qualified pilot, are allowed to carry out load test.
(2) load test should be carried out for two days and nights (allowing short-term traffic checks).
(3) Load Test at the beginning of a small amount of ore, then gradually increased to the full.
(4) load test must meet the following requirements:
A crusher without rapid vibration and noise.
B crusher to mine, and discharge provisions of the normal yield approximate.
C hydraulic station and work normally.
D lubrication system meets the following requirements:
To a kgf/cm2 oil pressure in the 0.8-1.5 range.
B back to the oil temperature does not exceed 60 ℃.
E wear pieces of the phenomenon there is no damage.
F electrical equipment and work normally.
5. Crusher maintenance


17. Crusher work Note:
(1) in the allocation of ore must be set to the middle, in Figure 14, will not be allowed to direct all broken ore cavity. Because it contained too easy to crusher, uneven wear liner.
The right to mine conditions are:
The ore was a uniform distribution of scattered broken cavity.
B all of the ore to be higher than the level of rolling acetabular wall
(2) ore crusher to the largest size, no equivalent to the mine mouth size, (the largest size to the ore block ≤ 85% to the mine mouth size) or they will lead to:
A crusher lower yield.
B crusher some other pieces of the damage.
(3) Starting crusher no load, the load will be starting the accident.
(4) Parking, we must first stop to the mining machine, and to have broken into the cavity from the ore crusher, the crusher parking.
(5) crusher work should carry out regular checks of the locking system and hydraulic pressure at work and found that dealing with problems in a timely fashion.


18. Crusher output
Crusher output, and feeding, feeding block, block discharge of size, physical and mechanical properties of minerals, such as the temperature, great changes in the scope, factory output is given under the conditions specified in the broad adoption of .


19. Rolling acetabular wall replacement
Rolling acetabular wall in the U-shaped screw adjustment ring between injection of zinc alloy, so that it closely integrated with the new installation or replacement of rolling acetabular wall, in the work of 6-8 hours later, should examine their retention, and once again tighten U-shaped screw.


20. Replacement of the walls of the cone crusher
Cone Crusher wall is fixed in the head with conical taper on the body between the two zinc alloy casting a new installation or replacement of the cone crusher new wall work 6-8 hours later, should examine their retention, shall be immediately found loose Retention.


21. Gear
The circular plate to friction and wear, and affected the clearance of gear changes, in order to guarantee the normal gear meshing must be cancelled with the end of additional pads, the pads should be equal to the thickness of the wear circular plate.


22. Bearings and sealing device Bowl
Bearing Bowl installation, attention to the rope Penghuai block oil ring (available in support of hardwood, such as wire rope between).
Assembly, the spherical bearing scraping inquiry should be conducted to ensure that broken cone and cylindrical Bowl in contact with each other spherical inner ring 0.35-0.5 mm should ensure that the annular gap.
Bearing Bowl is used around the perfusion of the Palestinian alloy lock nail in the Bowl bearing the shelves to prevent Bowl bush along the circumference Ho rotation.
Bowl-bearing frame and use of the bond (pin) fixed, and if found work Bowl-bearing frame and there are gaps must be dealt with immediately.


23. Cylindrical sleeve-with the support of the transition to the third, in order to prevent the rotating hub, and in the upper tank into the hub of zinc alloy, should be replaced when the new hub-the actual size of preparation, because crusher after long hours of work and working relations with the inevitable result change. If the gap generals led Bushing rupture occurred.


24. Conical hub
Sleeve and air eccentric shaft to a study, the injection of zinc alloy to prevent the sleeve rotation, zinc alloy to a full gap, zinc alloy thermal injection because of the sleeve may cause deformation, the new suite of inspection cone size d1, d2 and B, incorrect should be timely amended, manufacturing spare parts, should be eccentric sets diameter size of the actual preparation in order to maintain the original combination.


25. Spring
(1) the role of spring when the crusher is not broken into the protection of the crusher is not damaged, so spring pressure and crusher of the broken line, in the normal working hours crusher spring is fixed, and the only drop in the crushing chamber the crusher to iron overload sets in when you raise your support compressed spring phenomenon.
(2) crusher in the upper part of a normal working hours beating, which is not a normal phenomenon must be carefully analyzed reasons, and to take measures to rule out the possibility, if the wrong compression spring will not normal work, but the damage may occur parts, as will be compressed spring The increase from breaking force.
A crusher upper beating in the following reasons:
A mine to mine to uneven or excessive
B Mine contains too much to the small and powdered ore or excessive humidity.
C discharge mouth gap too small.


26. Exposed rotating machinery parts, we should shields, but the defensive cover by the user-owned.

 